Center

construction progress

  • The excavation works are 100% completed in Zones B1, B3, B4, B5, B6 and BK.
    100% completed in zone B2.
    100% completed in zone B1’.
    100% completed in zone B7.
    100% completed in zone B10.
    90% completed in zone B8.
    97% completed in zone B2’.
    70% completed in zone B9.
    80% completed in zone B10’.
    95% completed in zone B3.
  • The shoring works are completed in Zone B3.
  • The concrete works are in progress in buildings
  • A07 to A10, A16, A21 to A28 to A30, B04 to B08, B10, B11, C01 to C04, D03 to D14, E03 to E09, F01
    to F05 and block H.
  • The masonry, plaster and MEP embedded works are in progress in buildings
    A07 to A10, A21 till A26, B04, B05, B10, B11, C01 to C04, D03 to D14, E03 to E09 and F1 to F5.